Revelstoke Dam Penstock 5

[slideshow]

Revelstoke Ringer Crane Demo
Revelstoke Interior Welding
Revelstoke Dam Penstock Fabrication
Revelstoke Preparation

[/slideshow]

Location: Revelstoke BC

Installation of the 26ft diameter penstock for Unit #5 at the Revelstoke Dam required onsite welding and fabrication to CSA standards, proper execution of multiple critical lifts, management of high hazard confined spaces and the installation of a traveling platform capable of rolling 400ft up and down the interior of the penstock.